Disabling matrix project right after scheduled can cause combination to get aborted/never run

XMLWordPrintable

    • Icon: Improvement Improvement
    • Resolution: Unresolved
    • Icon: Minor Minor
    • matrix-project-plugin
    • None

      • Schedule matrix project
      • Disable it (before combinations are started)
      • Combinations started after that are never run (the run is not created) but parent's console log says:
      Triggering XXX » YY
      XXX » YY appears to be cancelled
      XXX » YY completed with result ABORTED
      

      It is misleading.